PMI-ACP · Question #375
Assuming all projects require the same amount of up-front investment, the project with the highest ______________ would be considered the best and undertaken first.
The correct answer is B. Internal Rate of Return (IRR). When projects have identical up-front investment costs, IRR is the best ranking metric because it expresses return as a percentage rate, making projects directly comparable regardless of scale. A higher IRR means a better return per dollar invested. NPV gives an absolute dollar v
Question
Assuming all projects require the same amount of up-front investment, the project with the highest ______________ would be considered the best and undertaken first.
Options
- AEarned Value Management (EVM)
- BInternal Rate of Return (IRR)
- CNet Present Value (NPV)
- DBudget at Completion (BAC)
How the community answered
(45 responses)- A2% (1)
- B82% (37)
- C7% (3)
- D9% (4)
Explanation
When projects have identical up-front investment costs, IRR is the best ranking metric because it expresses return as a percentage rate, making projects directly comparable regardless of scale. A higher IRR means a better return per dollar invested. NPV gives an absolute dollar value (better for comparing magnitude of return but requires knowing the discount rate). EVM is a performance monitoring tool, and BAC is simply the total planned budget - neither is used for project selection.
Topics
Community Discussion
No community discussion yet for this question.