nerdexam
PMIPMI

PMI-ACP · Question #375

PMI-ACP Question #375: Real Exam Question with Answer & Explanation

The correct answer is B: Internal Rate of Return (IRR). When projects have identical up-front investment costs, IRR is the best ranking metric because it expresses return as a percentage rate, making projects directly comparable regardless of scale. A higher IRR means a better return per dollar invested. NPV gives an absolute dollar v

Submitted by klara.se· Apr 18, 2026Value-driven Delivery

Question

Assuming all projects require the same amount of up-front investment, the project with the highest ______________ would be considered the best and undertaken first.

Options

  • AEarned Value Management (EVM)
  • BInternal Rate of Return (IRR)
  • CNet Present Value (NPV)
  • DBudget at Completion (BAC)

Explanation

When projects have identical up-front investment costs, IRR is the best ranking metric because it expresses return as a percentage rate, making projects directly comparable regardless of scale. A higher IRR means a better return per dollar invested. NPV gives an absolute dollar value (better for comparing magnitude of return but requires knowing the discount rate). EVM is a performance monitoring tool, and BAC is simply the total planned budget — neither is used for project selection.

Topics

#Project Selection#Financial Metrics#Internal Rate of Return (IRR)#Value Maximization

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions