PMI-ACP · Question #375
PMI-ACP Question #375: Real Exam Question with Answer & Explanation
The correct answer is B: Internal Rate of Return (IRR). When projects have identical up-front investment costs, IRR is the best ranking metric because it expresses return as a percentage rate, making projects directly comparable regardless of scale. A higher IRR means a better return per dollar invested. NPV gives an absolute dollar v
Question
Assuming all projects require the same amount of up-front investment, the project with the highest ______________ would be considered the best and undertaken first.
Options
- AEarned Value Management (EVM)
- BInternal Rate of Return (IRR)
- CNet Present Value (NPV)
- DBudget at Completion (BAC)
Explanation
When projects have identical up-front investment costs, IRR is the best ranking metric because it expresses return as a percentage rate, making projects directly comparable regardless of scale. A higher IRR means a better return per dollar invested. NPV gives an absolute dollar value (better for comparing magnitude of return but requires knowing the discount rate). EVM is a performance monitoring tool, and BAC is simply the total planned budget — neither is used for project selection.
Topics
Community Discussion
No community discussion yet for this question.