PMI-ACP · Question #309

PMI-ACP Question #309: Real Exam Question with Answer & Explanation

The three listed options are all legitimate Agile iteration artifacts: the Iteration Backlog (the list of work items committed to for the iteration), the Iteration Plan (how the team will execute the work), and the Iteration Burndown Chart (a progress-tracking graph for the itera

Submitted by yousef_jo· Apr 18, 2026Adaptive Planning

Question

Agile project management and product development use several types of documents specific to each iteration; they are known as "artifacts". All of the following documents are Agile iteration artifacts except:

Options

  • BIteration Backlog
  • CIteration Plan
  • DIteration Burndown Chart

Explanation

The three listed options are all legitimate Agile iteration artifacts: the Iteration Backlog (the list of work items committed to for the iteration), the Iteration Plan (how the team will execute the work), and the Iteration Burndown Chart (a progress-tracking graph for the iteration). Choice A — which was omitted from the question text but is marked correct — is most likely a project-level or traditional artifact (such as a Product Backlog, Project Charter, or Work Breakdown Structure) that spans the entire project rather than belonging to a single iteration. Project-level artifacts are not iteration artifacts.

Topics

#Agile Artifacts#Iteration Management#Agile Planning#Scrum Artifacts