nerdexam
PMIPMI

PMI-ACP · Question #210

PMI-ACP Question #210: Real Exam Question with Answer & Explanation

The correct answer is D: Monte Carlo. Monte Carlo simulation is a probabilistic risk analysis technique that runs thousands of simulated scenarios using variable inputs (such as team velocity ranges or task duration estimates) to produce a distribution of possible outcomes (e.g., project completion dates or cost rang

Submitted by paula_co· Apr 18, 2026Adaptive Planning

Question

Which term best describes an Agile project's approach to risk analysis?

Options

  • ARegression
  • BPareto
  • CQualitative
  • DMonte Carlo

Explanation

Monte Carlo simulation is a probabilistic risk analysis technique that runs thousands of simulated scenarios using variable inputs (such as team velocity ranges or task duration estimates) to produce a distribution of possible outcomes (e.g., project completion dates or cost ranges). Agile projects use Monte Carlo to quantify schedule and cost risk in a way that reflects real-world uncertainty. Regression is a statistical/testing term, Pareto is used for prioritization (80/20 rule), and Qualitative risk analysis ranks risks by likelihood and impact without numerical simulation.

Topics

#Risk Management#Quantitative Risk Analysis#Monte Carlo Simulation#Adaptive Planning

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions