The correct answer is B: No. Creating two sequential Update Row actions does not minimize processing time because they run one after the other rather than simultaneously.
Question
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution. After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen. You are creating a cloud flow that will use two Update Row actions to interact with Microsoft Dataverse. Neither of these actions are dependent on each other. You must minimize the amount of processing time require to complete the flow. You need to implement the actions in the cloud flow. Solution: Create two sequential Update Row actions. Does the solution meet the goal?
Options
- AYes
- BNo
Explanation
Creating two sequential Update Row actions does not minimize processing time because they run one after the other rather than simultaneously.
Common mistakes.
- A. Selecting Yes is incorrect because sequential execution inherently takes longer than parallel execution when two actions share no dependency on each other.
Concept tested. Sequential vs. parallel action execution in cloud flows