PL-400 · Question #359
A company performs an update to an existing column-bound Power Apps Component Framework (PCF) code component. You test the changes to the code component in the development environment. You then…
The correct answer is A. Import the PCF code component to the production environment directly from Visual Studio Code. If changes to a PCF component within a managed solution are not reflected after import, directly pushing the component from Visual Studio Code can force the update into the environment.
Question
Options
- AImport the PCF code component to the production environment directly from Visual Studio Code
- BPublish the form that uses the PCF code component in the production environment.
- CIncrement the PCF control version property in the manifest.xml file, and then reimport the solution
- DPublish the PCF code component in the production environment.
How the community answered
(32 responses)- A78% (25)
- B6% (2)
- C13% (4)
- D3% (1)
Why each option
If changes to a PCF component within a managed solution are not reflected after import, directly pushing the component from Visual Studio Code can force the update into the environment.
If a managed solution update fails to reflect changes for a PCF component, importing the component directly from Visual Studio Code using 'pac pcf push' can overwrite the existing component or create an unmanaged layer, ensuring the latest changes are deployed and visible in the environment.
Publishing the form only applies form-level customizations and does not address issues where the underlying PCF component itself was not updated or recognized by the environment after a solution import.
Incrementing the PCF control version property in the manifest.xml file and then reimporting the solution is the standard best practice for updating PCF components via managed solutions; however, if the managed solution process is failing to apply updates, a direct push might be used to force the change.
'Publish the PCF code component' is not a direct action or command within Power Apps environments for PCF components; they are deployed via solutions or direct development pushes.
Concept tested: PCF component update deployment
Source: null
Community Discussion
No community discussion yet for this question.