PGMP · Question #448
A program is near completion and the benefits will be delivered shortly. The program manager prepares to initiate program closeout activities to release the program resources. Before, initiating…
The correct answer is B. Obtain approval from the sponsor to close the program. Before initiating formal closeout activities and releasing resources, the program manager must obtain formal approval from the program sponsor to close the program. This is a governance gate - the sponsor holds the authority to authorize closure, and proceeding without approval…
Question
A program is near completion and the benefits will be delivered shortly. The program manager prepares to initiate program closeout activities to release the program resources. Before, initiating closeout and releasing the resources, what should the program manager do?
Options
- AReview the benefits management plan with the program sponsor
- BObtain approval from the sponsor to close the program
- CPrepare performance evaluations for all program personnel
- DPrepare performance evaluations for all project personnel
How the community answered
(30 responses)- A13% (4)
- B77% (23)
- C3% (1)
- D7% (2)
Explanation
Before initiating formal closeout activities and releasing resources, the program manager must obtain formal approval from the program sponsor to close the program. This is a governance gate - the sponsor holds the authority to authorize closure, and proceeding without approval could result in premature closure before benefits are confirmed or obligations are met. Option A (reviewing the benefits management plan) is a good practice but does not replace formal sponsor approval. Options C and D (performance evaluations) are closeout activities that happen after closure is authorized, not before.
Topics
Community Discussion
No community discussion yet for this question.