nerdexam
PMI

PGMP · Question #428

A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end. What should be completed first to close all appropriate contracts?

The correct answer is C. Assess all contracts to ensure all agreed conditions are met. Assessing all contracts to ensure all agreed conditions have been met is the foundational first step in contract closure because it establishes the factual basis for all subsequent closure activities. You cannot certify completion (A) without first verifying all conditions are…

Program Life Cycle - Closing Activities

Question

A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end. What should be completed first to close all appropriate contracts?

Options

  • ACertify contract completion
  • BConduct a procurement audit to review the procurement process
  • CAssess all contracts to ensure all agreed conditions are met
  • DReview contract management plan for completeness

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    14% (5)
  • C
    77% (27)
  • D
    3% (1)

Explanation

Assessing all contracts to ensure all agreed conditions have been met is the foundational first step in contract closure because it establishes the factual basis for all subsequent closure activities. You cannot certify completion (A) without first verifying all conditions are satisfied. A procurement audit (B) reviews the overall procurement process and lessons learned, which is a subsequent step after the contracts themselves are assessed. Reviewing the contract management plan for completeness (D) is part of the closure documentation process but is informed by the condition assessment. The logical sequence is: assess conditions met → certify completion → conduct procurement audit → document and close.

Topics

#Program Closure#Contract Management#Procurement Closure#Administrative Closure

Community Discussion

No community discussion yet for this question.

Full PGMP Practice