nerdexam
PMI

PGMP · Question #393

You are managing a project and the sponsor has removed the previous Project Manager on the project because they could not keep the project on budget. According to your current project budget, this…

The correct answer is B. Tell senior management the project is over budget by $245,000 with a plan to recover. The PMI Code of Ethics emphasizes honesty and transparency. A Project Manager has a professional obligation to report accurate project status regardless of personal consequences. Answer B is correct because it combines two critical elements: full disclosure of the budget…

Program Governance

Question

You are managing a project and the sponsor has removed the previous Project Manager on the project because they could not keep the project on budget. According to your current project budget, this project is over budget by $245,000. As the current Project Manager, you are afraid you will also be removed if you report this status. What is the best response you can tell senior management?

Options

  • AReport the delay to senior management and the reasons
  • BTell senior management the project is over budget by $245,000 with a plan to recover
  • CThe schedule is only two weeks behind so you don't report the delay
  • DDon't report the delay and begin looking for a new job

How the community answered

(51 responses)
  • A
    4% (2)
  • B
    67% (34)
  • C
    8% (4)
  • D
    22% (11)

Explanation

The PMI Code of Ethics emphasizes honesty and transparency. A Project Manager has a professional obligation to report accurate project status regardless of personal consequences. Answer B is correct because it combines two critical elements: full disclosure of the budget overrun AND a corrective action plan. Simply reporting the problem without a recovery plan (A) is less effective. Hiding the overrun (C, D) is dishonest and unethical - and the problem will eventually surface anyway, causing greater damage. Presenting management with both the problem and a plan demonstrates professional competence and integrity.

Topics

#Program Governance#Financial Management#Stakeholder Communication#Ethical Conduct

Community Discussion

No community discussion yet for this question.

Full PGMP Practice