PGMP · Question #372
A single-phase construction project is in the process of closing. There are a number of processes coming together as things finish up to complete the work of the project. Which of the following is cor
The correct answer is D. Close Project will come before Contract Closure. In PMI's framework, Close Project (an Integration Management process) is performed before Contract Closure (a Procurement Management process). Close Project covers administrative closure - obtaining formal acceptance, archiving records, and releasing resources - while Contract Cl
Question
A single-phase construction project is in the process of closing. There are a number of processes coming together as things finish up to complete the work of the project. Which of the following is correct?
Options
- AContract Closure will come before Close Project
- BClose Project happens only if the project is completed as planned
- CClose Project and Contract Closure happen at the same time
- DClose Project will come before Contract Closure
How the community answered
(47 responses)- A2% (1)
- B4% (2)
- D94% (44)
Explanation
In PMI's framework, Close Project (an Integration Management process) is performed before Contract Closure (a Procurement Management process). Close Project covers administrative closure - obtaining formal acceptance, archiving records, and releasing resources - while Contract Closure finalizes and settles each individual contract. Since contracts are a subset of the overall project, the project's administrative closure is initiated first, and then individual contracts are formally closed out. Option A reverses the order. Option B is wrong because Close Project must still be performed even if the project ends early (due to cancellation, etc.). Option C is wrong because they are distinct sequential processes, not simultaneous.