PGMP · Question #363
The project will be using a company to provide the technicians for a national network upgrade project. Presently, the team is receiving proposals to select the vendor that will do the work. In what…
The correct answer is D. Request Seller Responses. Request Seller Responses (also called Conduct Procurements in PMBOK 5+) is the process in which the project team solicits and receives bids, proposals, or quotations from prospective sellers. The key indicator in this question is that the team is 'receiving proposals' - they…
Question
The project will be using a company to provide the technicians for a national network upgrade project. Presently, the team is receiving proposals to select the vendor that will do the work. In what process is the team involved?
Options
- APlan Contracting
- BPlan Purchases and Acquisitions
- CSelect Sellers
- DRequest Seller Responses
How the community answered
(48 responses)- A2% (1)
- B4% (2)
- C10% (5)
- D83% (40)
Explanation
Request Seller Responses (also called Conduct Procurements in PMBOK 5+) is the process in which the project team solicits and receives bids, proposals, or quotations from prospective sellers. The key indicator in this question is that the team is 'receiving proposals' - they have already advertised the work and vendors are now submitting their responses. This is distinct from 'Select Sellers,' which comes next and involves evaluating those received proposals to choose a winner. 'Plan Purchases and Acquisitions' and 'Plan Contracting' are earlier planning-phase processes.