nerdexam
PMI

PGMP · Question #208

Tom is program manager for his organization. His program is scheduled to last ten months and has a cost estimate for the program of $550,000. It is now month nine and Tom reports that he actually has

The correct answer is C. A poor cost estimate could affect the organization's decisions to invest the funds elsewhere .. A positive cost variance means the program spent less than budgeted, which seems favorable. However, it can signal that the original cost estimate was inaccurate and inflated. If management was told $550,000 was needed, they committed those funds to this program and did not inves

Strategic Alignment

Question

Tom is program manager for his organization. His program is scheduled to last ten months and has a cost estimate for the program of $550,000. It is now month nine and Tom reports that he actually has a cost variance of a positive $56,000. While Tom is pleased, the new management is not. Why is a positive cost variance not necessarily good news?

Options

  • AA poor cost estimate prevented the organization from adding things to the program scope.
  • BTom has overestimated the cost of the program.
  • CA poor cost estimate could affect the organization's decisions to invest the funds elsewhere .
  • DTom has forgot to include deliverables in the program.

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    23% (7)
  • C
    58% (18)
  • D
    13% (4)

Explanation

A positive cost variance means the program spent less than budgeted, which seems favorable. However, it can signal that the original cost estimate was inaccurate and inflated. If management was told $550,000 was needed, they committed those funds to this program and did not invest them elsewhere. A significantly inflated estimate means the organization may have foregone other profitable investments or opportunities based on flawed financial planning. This is why accurate estimating matters - overestimating locks up capital unnecessarily and undermines organizational decision-making about resource allocation.

Topics

#Cost Variance#Program Financial Management#Strategic Resource Allocation#Opportunity Cost

Community Discussion

No community discussion yet for this question.

Full PGMP Practice