PGMP · Question #145

You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What t

The correct answer is D. Work that has been completed and uncompleted work. When terminating a vendor contract, the two required documentation items are the work that has been completed and the work that remains uncompleted, establishing payment obligations and identifying remaining scope gaps.

Program Governance

Question

You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?

Options

  • AContract and the quality measurements for the vendor's work
  • BThe scope verification document and the termination notice
  • CContract and scope verification process documents
  • DWork that has been completed and uncompleted work

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    11% (3)
  • C
    14% (4)
  • D
    71% (20)

Why each option

When terminating a vendor contract, the two required documentation items are the work that has been completed and the work that remains uncompleted, establishing payment obligations and identifying remaining scope gaps.

AContract and the quality measurements for the vendor's work

Quality measurements assess vendor performance against standards but are not the primary paired documentation required to execute a contract termination.

BThe scope verification document and the termination notice

Scope verification documents and termination notices are not the standard paired documentation required for settling a vendor contract termination.

CContract and scope verification process documents

Scope verification process documents describe how verification is conducted but do not capture the actual work status needed to fairly settle a contract termination.

DWork that has been completed and uncompleted workCorrect

Documenting completed work establishes what deliverables and effort the vendor has provided, forming the basis for determining payment owed. Documenting uncompleted work identifies the remaining scope gap that must be addressed through alternative means, enabling an orderly transition and avoiding program schedule disruption.

Concept tested: Vendor contract termination documentation requirements

Source: https://www.pmi.org/pmbok-guide-standards/foundational/program-management

Topics

#Contract Termination#Procurement Management#Program Closure#Contract Documentation