nerdexam
PMI

PFMP · Question #88

Which process group includes "Manage Supply and Demand"?

The correct answer is B. Aligning. The Manage Supply and Demand process belongs to the Aligning process group in PMI's Standard for Portfolio Management, as it balances resource capacity against portfolio component needs.

Portfolio Optimization

Question

Which process group includes "Manage Supply and Demand"?

Options

  • AMonitoring
  • BAligning
  • CAuthorizing and Controlling
  • DDefining

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    90% (28)
  • C
    3% (1)

Why each option

The Manage Supply and Demand process belongs to the Aligning process group in PMI's Standard for Portfolio Management, as it balances resource capacity against portfolio component needs.

AMonitoring

The Monitoring process group focuses on collecting and reporting portfolio performance data, not on managing the balance of resources and demand.

BAligningCorrect

Manage Supply and Demand is in the Aligning process group because it focuses on balancing organizational capacity (supply) against the aggregate needs of portfolio components (demand), which is an alignment activity ensuring the portfolio remains resourced, feasible, and optimized relative to organizational constraints.

CAuthorizing and Controlling

The Authorizing and Controlling process group involves approving components and controlling changes to the portfolio, not managing ongoing resource supply versus component demand.

DDefining

The Defining process group establishes the portfolio strategic plan and roadmap, not the ongoing operational balancing of supply and demand.

Concept tested: Portfolio management process group classification

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Portfolio Management Process Groups#Aligning Process Group#Supply and Demand Management#Resource Optimization

Community Discussion

No community discussion yet for this question.

Full PFMP Practice