PFMP · Question #509
Portfolios include a lot of work and as a portfolio manager you need to keep an eye on the value realization while maintaining the strategic alignment. You are currently aggregating value delivered…
The correct answer is A. Roadmap, Portfolio Management Plan, Portfolio Reports. When aggregating value delivered by portfolio components, the inputs used are the Roadmap, Portfolio Management Plan, and Portfolio Reports. The Roadmap provides strategic context and timelines, the Portfolio Management Plan provides the governance framework, and Portfolio…
Question
Portfolios include a lot of work and as a portfolio manager you need to keep an eye on the value realization while maintaining the strategic alignment. You are currently aggregating value delivered by the portfolio components. What can you use to help you in this context?
Options
- ARoadmap, Portfolio Management Plan, Portfolio Reports
- BRoadmap, Portfolio Management Plan, Portfolio Reports, Portfolio Process Assets, Portfolio
- CRoadmap, Portfolio Management Plan, Portfolio Reports, Portfolio Process Assets
- DRoadmap, Portfolio Management Plan, Portfolio Reports, Portfolio Process Assets, Portfolio
How the community answered
(51 responses)- A71% (36)
- B8% (4)
- C18% (9)
- D4% (2)
Explanation
When aggregating value delivered by portfolio components, the inputs used are the Roadmap, Portfolio Management Plan, and Portfolio Reports. The Roadmap provides strategic context and timelines, the Portfolio Management Plan provides the governance framework, and Portfolio Reports provide current performance and value data. Options B and D add 'Portfolio Process Assets' and 'Portfolio' as additional items, but these are not standard inputs to the value aggregation step. Option A correctly identifies the three core inputs needed for this process.
Topics
Community Discussion
No community discussion yet for this question.