PFMP · Question #329

PFMP Question #329: Real Exam Question with Answer & Explanation

The correct answer is C: Portfolio Component Inventory. See the full explanation below for the reasoning.

Portfolio Definition

Question

The portfolio manager defines the portfolio based on a listing of already existing work in the organization and selects the right components in order to be able to prioritize them. What do you use for defining the portfolio based on the listing of work?

Options

  • APrioritization
  • BInventory of Work
  • CPortfolio Component Inventory
  • DElicitation technique

Topics

#Portfolio Definition#Portfolio Components#Portfolio Component Inventory