PFMP · Question #218

PFMP Question #218: Real Exam Question with Answer & Explanation

The correct answer is B: Stakeholder communication matrix. See the full explanation below for the reasoning.

Communication and Stakeholder Engagement

Question

Delays in many component projects have led to a decision to increase the frequency of the portfolio review meeting to every 2 months instead of quarterly in order to monitor the portfolio more closely, requiring a change in the frequency of reporting cycles. Where should the portfolio manager maintain this information?

Options

  • APortfolio charter
  • BStakeholder communication matrix
  • CGovernance decisions
  • DCommunication calendar

Topics

#Portfolio Communication#Stakeholder Management#Communication Matrix#Reporting Cycles