The correct answer is C: Develop and review the risk register.. See the full explanation below for the reasoning.

Risk Management

Question

An organization establishes a new portfolio to initiate a new division. A new management team from a wide variety of competitors is hired. The portfolio manager reviews the potential portfolio risks with the new management team members, who have very different views of the risks based on various backgrounds and levels of experience. Which approach should the portfolio manager use to develop a common understanding of the portfolio risks among team members?

Options

  • APerform and review the risk prioritization.
  • BPerform and review a Monte Carlo simulation.
  • CDevelop and review the risk register.
  • DDevelop and review a risk probability and impact matrix.

Topics

#Portfolio Risk Management#Risk Register#Stakeholder Alignment#Risk Communication