nerdexam
Pegasystems

PEGACSSA_V6.2 · Question #62

Pegasystems PEGACSA_v6.2 Exam When integrating with external systems, one concern is managing how the connection information may vary as the application migrates from Development through Production…

The correct answer is A. Global Resource Settings. See the full explanation below for the reasoning.

Question

Pegasystems PEGACSA_v6.2 Exam When integrating with external systems, one concern is managing how the connection information may vary as the application migrates from Development through Production. This problem is solved by using which of the following PRPC techniques? (Choose One)

Options

  • AGlobal Resource Settings
  • BDynamic Class Referencing
  • CDeclare Pages
  • DCircumstanced Data Transform rules

How the community answered

(24 responses)
  • A
    75% (18)
  • B
    4% (1)
  • C
    13% (3)
  • D
    8% (2)

Community Discussion

No community discussion yet for this question.

Full PEGACSSA_V6.2 Practice