When is it appropriate to use a spin-off? (Choose One)

The correct answer is C. When you wish to start a different part of the process while continuing down the current process path. See the full explanation below for the reasoning.

Question

When is it appropriate to use a spin-off? (Choose One)

Options

  • AWhen you wish to run calculations in a separate thread from the current process
  • BWhen you wish to make a long-running SOAP service call asynchronously
  • CWhen you wish to start a different part of the process while continuing down the current process path
  • DWhen you wish to call multiple connector rules concurrently

How the community answered

(49 responses)
  • A
    8% (4)
  • B
    4% (2)
  • C
    76% (37)
  • D
    12% (6)