Which two of the following statements are most accurate about the Split-For-Each and Split-Join shapes? (Choose Two)
The correct answer is A. Both shapes allow you to continue processing when ANY or ALL of the sub processes complete B. Split-Join allows you to execute different sub-flows whereas Split-For-Each calls the same process on. See the full explanation below for the reasoning.
Question
Which two of the following statements are most accurate about the Split-For-Each and Split-Join shapes? (Choose Two)
Options
- ABoth shapes allow you to continue processing when ANY or ALL of the sub processes complete
- BSplit-Join allows you to execute different sub-flows whereas Split-For-Each calls the same process on
- CSplit-For-Each allows you to execute different sub-flows whereas Split-Join calls the same process on
- DBoth shapes create separate Threads for sub-processes they create
- ESplit-For-Each can only be used when iterating over a list of work objects
How the community answered
(43 responses)- A81% (35)
- C12% (5)
- D2% (1)
- E5% (2)