When is it appropriate to use a spin-off? (Choose One)
The correct answer is C. When you wish to start a different part of the process while continuing down the current process path. See the full explanation below for the reasoning.
Question
When is it appropriate to use a spin-off? (Choose One)
Options
- AWhen you wish to run calculations in a separate thread from the current process
- BWhen you wish to make a long-running SOAP service call asynchronously
- CWhen you wish to start a different part of the process while continuing down the current process path
- DWhen you wish to call multiple connector rules concurrently
How the community answered
(42 responses)- A17% (7)
- B10% (4)
- C71% (30)
- D2% (1)