Pegasystems
PEGACSSA71V1 · Question #4
If an agent runs at 2:30 PM and if it's configured to run at 30 minutes interval with a max record of 50, when does the agent run next time? (Choose One)
The correct answer is C. 30 minutes after the last run is completed. See the full explanation below for the reasoning.
Question
If an agent runs at 2:30 PM and if it's configured to run at 30 minutes interval with a max record of 50, when does the agent run next time? (Choose One)
Options
- ADepends on the number of PRPC nodes
- B30 minutes after the last run is started
- C30 minutes after the last run is completed
- DOne hour after the last run because all agents can run only once every hour
How the community answered
(31 responses)- A6% (2)
- B16% (5)
- C74% (23)
- D3% (1)
Community Discussion