What is the key difference between BPM application development and traditional application development? (Choose One)

The correct answer is A. A BPM application is process-centric (all elements of the application depend upon the process). See the full explanation below for the reasoning.

Question

What is the key difference between BPM application development and traditional application development? (Choose One)

Options

  • AA BPM application is process-centric (all elements of the application depend upon the process)
  • BIn a BPM application, elements of the application ?such as UI, logic, and data ?cannot be modular
  • CA traditional application cannot be used in an N-tier environment
  • DA traditional application allows for direct execution of the business process, while a BPM application does not

How the community answered

(49 responses)
  • A
    76% (37)
  • B
    6% (3)
  • C
    4% (2)
  • D
    14% (7)