What does "Build For Change? mean? (Choose One)

The correct answer is C. Build applications that are more easily adaptable to inevitable business change. See the full explanation below for the reasoning.

Question

What does "Build For Change? mean? (Choose One)

Options

  • ABuild applications without change control, in order to complete projects more quickly
  • BLaunch applications as soon as possible so that performance testing can be done in Production
  • CBuild applications that are more easily adaptable to inevitable business change
  • DBusiness architects initially build PRPC applications and system architects subsequently change them

How the community answered

(62 responses)
  • A
    3% (2)
  • B
    10% (6)
  • C
    84% (52)
  • D
    3% (2)