What is the primary difference between a Validate rule and a Constraints rule? (Choose One)

The correct answer is C. Constraints rules are evaluated procedurally, while Validate rules are executed declaratively. See the full explanation below for the reasoning.

Question

What is the primary difference between a Validate rule and a Constraints rule? (Choose One)

Options

  • AA Validate rule can reference either Validate rules or Constraints rules, while a Constraints rule can only
  • BConstraints rules are evaluated declaratively, while Validate rules are executed procedurally
  • CConstraints rules are evaluated procedurally, while Validate rules are executed declaratively
  • DA Validate rule indicates the specific property that fails validation, while a Constraints rule does not indicate

How the community answered

(15 responses)
  • B
    7% (1)
  • C
    80% (12)
  • D
    13% (2)

Community Discussion

No community discussion yet for this question.

Full PEGACSA_V6.2 Practice