Roger receives an assignment during business hours on Tuesday, the 14th. The assignment is governed by the following service level. Assuming a Monday-Friday, 5-day work-week with no holidays or time…

The correct answer is B. Friday, the 17th. See the full explanation below for the reasoning.

Question

Roger receives an assignment during business hours on Tuesday, the 14th. The assignment is governed by the following service level. Assuming a Monday-Friday, 5-day work-week with no holidays or time off, determine the dayon which the urgency adjustment caused bythe service level will reach 70.

Exhibit

PEGACPBA71V1 question #16 exhibit

Options

  • AThursday, the 23rd
  • BFriday, the 17th
  • CMonday, the 20th
  • DWednesday, the 22nd

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    82% (28)
  • C
    6% (2)
  • D
    9% (3)

Community Discussion

No community discussion yet for this question.

Full PEGACPBA71V1 Practice