nerdexam
Pegasystems

PEGACLSA_62V2 · Question #74

Several development teams work on different enhancements in the same RuleSet simultaneously and it is not known ahead which enhancements will go into production first. Which of the following…

The correct answer is A. Create branch RuleSets for each development team. See the full explanation below for the reasoning.

Question

Several development teams work on different enhancements in the same RuleSet simultaneously and it is not known ahead which enhancements will go into production first. Which of the following approached is best suitable for this requirement? (Choose One)

Options

  • ACreate branch RuleSets for each development team
  • BCreate multiple RuleSets and merge the RuleSets later
  • CUse the private check-out feature
  • DCreate multiple RuleSet versions

How the community answered

(14 responses)
  • A
    71% (10)
  • B
    7% (1)
  • C
    14% (2)
  • D
    7% (1)

Community Discussion

No community discussion yet for this question.

Full PEGACLSA_62V2 Practice