Palo_Alto_Networks
PCNSE6 · Question #88
Which link is used by an Active-Passive cluster to synchronize session information?
The correct answer is A. The Data Link. See the full explanation below for the reasoning.
Question
Which link is used by an Active-Passive cluster to synchronize session information?
Options
- AThe Data Link
- BThe Control Link
- CThe Uplink
- DThe Management Link
How the community answered
(31 responses)- A74% (23)
- B16% (5)
- C3% (1)
- D6% (2)
Community Discussion
No community discussion yet for this question.