In which step of the `continual improvement model' is an improvement plan implemented?

The correct answer is C. Take action. See the full explanation below for the reasoning.

Question

In which step of the `continual improvement model' is an improvement plan implemented?

Options

  • AWhat is the vision?
  • BHow do we get there?
  • CTake action
  • DDid we get there?

How the community answered

(58 responses)
  • A
    16% (9)
  • B
    3% (2)
  • C
    71% (41)
  • D
    10% (6)