The addition, modification or removal of an authorized, planned or supported service or service component and its associated documentation is a definition of what?

The correct answer is A. A change. See the full explanation below for the reasoning.

Question

The addition, modification or removal of an authorized, planned or supported service or service component and its associated documentation is a definition of what?

Options

  • AA change
  • BA change model
  • CA change request
  • DA change advisory board

How the community answered

(17 responses)
  • A
    82% (14)
  • C
    6% (1)
  • D
    12% (2)