What is typically needed to assign complex incidents to support groups?
The correct answer is B. The incident category. See the full explanation below for the reasoning.
Question
What is typically needed to assign complex incidents to support groups?
Options
- AThe incident priority
- BThe incident category
- CA change schedule
- DA self-help tool
How the community answered
(23 responses)- A9% (2)
- B83% (19)
- C4% (1)
- D4% (1)