PeopleCert
PC0-001 · Question #616
Which statement about a `continual improvement register' is CORRECT?
The correct answer is D. It should be re-prioritized as ideas are documented. See the full explanation below for the reasoning.
Question
Which statement about a `continual improvement register' is CORRECT?
Options
- AIt should be managed at the senior level of the organization
- BIt should be used to capture user demand
- CThere should only be one for the whole organization
- DIt should be re-prioritized as ideas are documented
How the community answered
(15 responses)- A13% (2)
- C7% (1)
- D80% (12)
Community Discussion
No community discussion yet for this question.