How many times should each stage of the Plan, Do, Check, Act (PDCA) cycle be visited?

The correct answer is D. The entire cycle should be repeated multiple times to implement Continual Improvement. See the full explanation below for the reasoning.

Question

How many times should each stage of the Plan, Do, Check, Act (PDCA) cycle be visited?

Options

  • AEach stage should be carried out once in the order Plan-Do-Check-Act
  • BThere should be a single Plan,then the Do-Check-Act cycle should be repeated multiple times to
  • CThere should be a single Plan and Do,then Check and Act should be carried out multiple times to
  • DThe entire cycle should be repeated multiple times to implement Continual Improvement

How the community answered

(49 responses)
  • A
    6% (3)
  • B
    4% (2)
  • C
    14% (7)
  • D
    76% (37)