PeopleCert
PC0-001 · Question #411
A plan for managing the end of a supplier contract should be created when?
The correct answer is A. The contract is being negotiated. See the full explanation below for the reasoning.
Question
A plan for managing the end of a supplier contract should be created when?
Options
- AThe contract is being negotiated
- BThe contract is about to be ended
- CThe Supplier Manager decides that there is a risk the contract might need to end soon
- DThe contract has been agreed
How the community answered
(33 responses)- A73% (24)
- B3% (1)
- C15% (5)
- D9% (3)
Community Discussion
No community discussion yet for this question.