Which of the following Availability Management activities are considered to be proactive as opposed to reactive? (1) Risk assessment (2) Testing of resilience mechanisms (3) Monitoring of component…

The correct answer is B. 1 and 2 only. See the full explanation below for the reasoning.

Question

Which of the following Availability Management activities are considered to be proactive as opposed to reactive? (1) Risk assessment (2) Testing of resilience mechanisms (3) Monitoring of component availability

Options

  • AAll of the above
  • B1 and 2 only
  • C1 and 3 only
  • D2 and 3 only

How the community answered

(48 responses)
  • A
    2% (1)
  • B
    83% (40)
  • C
    4% (2)
  • D
    10% (5)