"Planning and managing the resources required to deploy a release into production" is a purpose of which part of the Service Lifecycle?
The correct answer is C. Service Transition. See the full explanation below for the reasoning.
Question
"Planning and managing the resources required to deploy a release into production" is a purpose of which part of the Service Lifecycle?
Options
- AService Operation
- BService Strategy
- CService Transition
- DContinual Service Improvement
How the community answered
(53 responses)- A11% (6)
- B6% (3)
- C79% (42)
- D4% (2)
Community Discussion