PC0-001 · Question #267

Which of the following describes risk proximity?

The correct answer is D. The timeframe for when the risk might materialize. See the full explanation below for the reasoning.

Question

Which of the following describes risk proximity?

Options

  • AThe timeframe over which the risk mitigation actions should be implemented
  • BThe schedule for the risk management activities related to a plan
  • CThe timeframe over which a risk will be monitored by the risk owner
  • DThe timeframe for when the risk might materialize

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    4% (1)
  • C
    15% (4)
  • D
    73% (19)