PeopleCert
PC0-001 · Question #233
PC0-001 Question #233: Real Exam Question with Answer & Explanation
The correct answer is D. Priority should be based on impact and urgency. See the full explanation below for the reasoning.
Question
Which of the following statements correctly states the relationship between urgency, priority and impact?
Options
- AImpact, priority and urgency are independent of each other
- BUrgency should be based on impact and priority
- CImpact should be based on urgency and priority
- DPriority should be based on impact and urgency
Community Discussion
No community discussion yet for this question.