A Service design package (SDP) would normally be produced for which of the following? 1. A new IT service 2. A major change to an IT service 3. An emergency change to an IT service 4. An IT service…
The correct answer is B. 1, 2 and 4 only. See the full explanation below for the reasoning.
Question
A Service design package (SDP) would normally be produced for which of the following? 1. A new IT service 2. A major change to an IT service 3. An emergency change to an IT service 4. An IT service retirement
Options
- A2, 3 and 4 only
- B1, 2 and 4 only
- CNone of the above
- DAll of the above
How the community answered
(30 responses)- A17% (5)
- B70% (21)
- C7% (2)
- D7% (2)