PC0-001 · Question #124
Which of the following availability management activities is/are considered to be proactive as opposed to reactive? 1. Monitoring system availability 2. Designing availability into a proposed solution
The correct answer is D. 2 only. See the full explanation below for the reasoning.
Question
Which of the following availability management activities is/are considered to be proactive as opposed to reactive? 1. Monitoring system availability 2. Designing availability into a proposed solution
Options
- ANone of the above
- BBoth of the above
- C1 only
- D2 only
How the community answered
(23 responses)- A13% (3)
- B4% (1)
- C4% (1)
- D78% (18)