Which one of the following is NOT a responsibility of the service transition stage of the service lifecycle?

The correct answer is B. To design and develop capabilities for service management. See the full explanation below for the reasoning.

Question

Which one of the following is NOT a responsibility of the service transition stage of the service lifecycle?

Options

  • ATo ensure that a service can be managed and operated in accordance with constraints specified during
  • BTo design and develop capabilities for service management
  • CTo provide good-quality knowledge and information about services
  • DTo plan the resources required to manage a release

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    83% (24)
  • C
    10% (3)
  • D
    3% (1)