nerdexam
Amazon

PAS-C01 · Question #35

A company is running SAP S/4HANA on AWS. The company has deployed its current database infrastructure on a u-12tb1.112xlarge Amazon EC2 instance that uses default tenancy and SUSE Linux Enterprise Ser

The correct answer is C. Use the AWS CLI to stop the current instance. Create an AMI from the current instance. Use the. https://docs.aws.amazon.com/sap/latest/sap-hana/migrating-hana-to-hm.html

Operation and Maintenance of SAP Workloads on AWS

Question

A company is running SAP S/4HANA on AWS. The company has deployed its current database infrastructure on a u-12tb1.112xlarge Amazon EC2 instance that uses default tenancy and SUSE Linux Enterprise Server for SAP 15 SP1. The company must scale its SAP HANA database to an instance with more RAM. An SAP solutions architect needs to migrate the database to a u- 18tb1.metal High Memory instance. How can the SAP solutions architect meet this requirement?

Options

  • AUse the AWS Management Console to stop the current instance. Change the instance type to u-
  • BUse the AWS CLI to stop the current instance. Change the instance type to u-18tb1.metal. Start
  • CUse the AWS CLI to stop the current instance. Create an AMI from the current instance. Use the
  • DUse the AWS Management Console to stop the current instance. Create an AMI from the current

How the community answered

(51 responses)
  • A
    16% (8)
  • B
    4% (2)
  • C
    75% (38)
  • D
    6% (3)

Explanation

https://docs.aws.amazon.com/sap/latest/sap-hana/migrating-hana-to-hm.html

Topics

#EC2 Instance Migration#SAP HANA Scaling#AWS AMI#High Memory Instances

Community Discussion

No community discussion yet for this question.

Full PAS-C01 Practice