What are the 4 activities required for an upgrade of The Profile Generator?
The correct answer is A. Migrate the report tree B. Check the Profile Generation activation C. Upgrade the roles and default tables (su25) D. Conversion of manually created profiles to roles if necessary (su25). See the full explanation below for the reasoning.
Question
What are the 4 activities required for an upgrade of The Profile Generator?
Options
- AMigrate the report tree
- BCheck the Profile Generation activation
- CUpgrade the roles and default tables (su25)
- DConversion of manually created profiles to roles if necessary (su25)
How the community answered
(24 responses)- A100% (24)
Community Discussion