In the standard delivery system, what isthe maximum number of components you can use for the primary cost component split of activities and the cost component split of cost of goods sold?

The correct answer is B. 120. See the full explanation below for the reasoning.

Question

In the standard delivery system, what isthe maximum number of components you can use for the primary cost component split of activities and the cost component split of cost of goods sold?

Options

  • A160
  • B120
  • C40
  • D100

How the community answered

(62 responses)
  • A
    13% (8)
  • B
    79% (49)
  • C
    3% (2)
  • D
    5% (3)