SAP
P_S4FIN_1909 · Question #94
You create a G/L account and set the cost element category to 42 (assessment). In what table is the cost element category updated? Please choose the correct answer.
The correct answer is A. CSKB: Cost Elements (Data Dependent on Controlling Area). See the full explanation below for the reasoning.
Question
You create a G/L account and set the cost element category to 42 (assessment). In what table is the cost element category updated? Please choose the correct answer.
Options
- ACSKB: Cost Elements (Data Dependent on Controlling Area)
- BCSKA: Cost Elements (Data Dependent on chart of Accounts)
- CSKB1: G/L Account Master (Company Code)
- DSKA1: G/L Account Master (Chart of Accounts)
How the community answered
(23 responses)- A83% (19)
- B4% (1)
- C4% (1)
- D9% (2)
Community Discussion