nerdexam
SAP

P_ADM_SEC_70 · Question #64

When is it acceptable not to take action on an identified risk?

The correct answer is D. When the cost of the countermeasure outweighs the value of the asset and the potential loss. See the full explanation below for the reasoning.

Question

When is it acceptable not to take action on an identified risk?

Options

  • ANever. Good security has to address and reduce all risks.
  • BWhen political issues prevent this type of risk from being addressed.
  • CWhen the necessary countermeasure is too complex.
  • DWhen the cost of the countermeasure outweighs the value of the asset and the potential loss.

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    9% (2)
  • D
    82% (18)

Community Discussion

No community discussion yet for this question.

Full P_ADM_SEC_70 Practice