P2180-089 · Question #4
When a process allows for one of the endpoints to be updated on a schedule basis, after hours for instance, what should be selected in the Use Case Table?
The correct answer is B. Batch. See the full explanation below for the reasoning.
Question
When a process allows for one of the endpoints to be updated on a schedule basis, after hours for instance, what should be selected in the Use Case Table?
Options
- ANear Real Time.
- BBatch.
- COutbound.
- DInbound.
How the community answered
(19 responses)- A5% (1)
- B84% (16)
- C5% (1)
- D5% (1)
Community Discussion
No community discussion yet for this question.