If 'admin' user is running a query, what percentage of resources are available when Guaranteed Resource Allocation (GRA) is Enabled?

The correct answer is D. Typically half of the resources while other resource groups are active. See the full explanation below for the reasoning.

Question

If 'admin' user is running a query, what percentage of resources are available when Guaranteed Resource Allocation (GRA) is Enabled?

Options

  • AThe maximum GRA assigned to the ADMIN group.
  • BThe maximum GRA assigned to the PUBLIC group.
  • C100% of the resources while other resource groups are active.
  • DTypically half of the resources while other resource groups are active.

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    11% (3)
  • C
    4% (1)
  • D
    82% (23)