Which statement about the job schedule is NOT correct?
The correct answer is B. A schedule can be used to define the start time of a job. See the full explanation below for the reasoning.
Question
Which statement about the job schedule is NOT correct?
Options
- AA schedule can be used to define the end time of a job.
- BA schedule can be used to define the start time of a job.
- CA schedule can be used to define the frequency of a job.
- DA schedule can be used to define the dependency between 2 jobs.
How the community answered
(22 responses)- A5% (1)
- B82% (18)
- C9% (2)
- D5% (1)