Using a Job Sequence, which of the following tasks CANNOT be performed?
The correct answer is D. Create multiple Exception Handlers stages to handle different types of failures. See the full explanation below for the reasoning.
Question
Using a Job Sequence, which of the following tasks CANNOT be performed?
Options
- ADefine specific user variables and make them available within a Job Sequence
- BDrop a database table using a script, then start two different parallel jobs in sequence when a file
- CRun two different parallel jobs in sequence and use job parameters to pass different
- DCreate multiple Exception Handlers stages to handle different types of failures
How the community answered
(27 responses)- A4% (1)
- B4% (1)
- C15% (4)
- D78% (21)